Specialist construction and engineering lawyer Julian Cohen looks at your legal problems. We are a Main Contractor. Our standard form of sub-contract does not contain any express mention of our right to set-off contra-charges (etc) against payments that would otherwisw be due to our sub-contractor. Are we are legally entitled to set-off sums against the next interim payment?