Claims under the ACP Conditions
Authors
Citation
Asian Architect & Contractor, v.26, no.11, 1997, pp. 142-143
Abstract
A rare case under the General Conditions of Contract for the Airport Core Prgramme Civil Engineering Works (the ACP Conditions) will soon be published in the law reports. In A-G v Trafalgar House Construction (Asia) Ltd and Others, to be reported as [1996] 4 HKC 1, the Government opposed an adjudicatior hearing a common law claim for damages for breach of contract. This month J.A. McInnis looks at the jurisdiction of the adjudicator under the ACP Conditions and the distinction between claims under the contract and common claims for damages for breach of contract.
(1) Claims under the contract versus claims for breach of contract
(2) The facts
(3) The adjudicator's jurisdiction
(4) Conclusion