Symbolic of the move of Grade A-quality office developments away from crowded, expensive Central District and toward what other countries call the suburbs, the Cityplaza 3- Cityplaza 4 project is also an excellent example of good construction practices, as discussed by Ludwig Reichhold, the project manager for main contractor Dragages et Travaux Publics (HK) Ltd.
與其他現代化國家一樣,本港新建成的甲級商業大廈,已逐漸偏離傳統的商業中心區——中環,向東遷移至灣仔、銅鑼灣、甚至鰂魚涌,太古城中心第三、四期,正是商業區東移的例證。
太古城中心三、四期的地盤經理陸偉豪表示,該兩座商業大廈乃以全機械化方式建築,堪稱建築工程的典範。
(1) Background
太古城的「大門」
(2) Contractor involvement
(3) Environment and method
地基與地庫
(4) Post-tensioned slabs
後加拉力樓板
(5) High-strength concrete
高强度混凝土
(6) Inherent problems
温度問題
(7) Special mix design
煤灰應用
(8) Construction cycle
建築周期
(a) Corewalls
核心牆
(b) Columns
支柱
(c) Slabs
樓板
(9) Four-day construction cycle
四日建築周期
(10) Fully mechanised
全機械化
(11) Curtainwall
(12) Ancillary works
(13) Traffic, noise barriers
交通、噪音限制
(14) Statistics