Reconstruction of Princess Margaret Hospital: narrow site, detailed planning 瑪嘉烈醫院改建工程: 工地狹窄籌備精密
Authors
Citation
建築承造雜誌, May/Jun, 1996, pp. 58-59
Abstract
The reconstruciton of Princess Margaret Hospital has required some detailed planning to avoid disrupting the sensitive functions of the facility. Mr Au Koon Shan, Construction manager for main contractor Dickson Construction Co Ltd, explained the construction details to Construction & Contract News.
(1) Project scope
(2) Construction details
瑪嘉烈醫院第一期改建工程已經完成。改建工程於95年4月1日展開,分兩期進行,暫定於97年4月全部竣工。總承建商德信建築有限公司建築部經理區冠山向建築承造雜誌詳述了工程進展的情況。
Description
Building Name: Princess Margaret Hospital
Building Type(s): Hospitals
Architect: Architectural Services Department
Subject
Type
Article
Format
Date
1996
Language
en,zh