Law: questions & answers

Citation
Asian Architect & Contractor, v.30, no.1, 2001, pp. 47
Abstract
Specialist construction and engineering lawyer Julian Cohen looks at your legal problems. We are a Main Contractor. Our standard form of sub-contract does not contain any express mention of our right to set-off contra-charges (etc) against payments that would otherwise be due to our sub-contractor. Are we are legally entitled to set-off sums against the next interim payment? Julian Cohen is a Solicitor and Senior Associate specialising in Construction and Engineering in Masons Hong Kong Office. He can be contacted on (852) 2521 5621 or by e-mail: julian.cohen@masons.com If you have any particular questions you would like anwering please submit them to the editor. Unfortunately separtate correspondence with individuals cannot be entered into.
Description
Subject
Type
Article
Format
Date
2001
Language
en