Problems no problem to experienced builder

Authors
Citation
Building journal Hong Kong China, Aug, 1990, pp. 74-76
Abstract
A five-day-a-floor construction cycle, instead of the planned eight-day-per-floor, will allow a handover of the 42-storey ManuLife Tower in North Point in November 1990, more than two months ahead of schedule, says main contractor Shui On Construction Co Ltd. (1) Projcect details (2) Overcoming adversity (3) Project factors (4) Construction schedule (5) Project participants